Catch up on the latest GSA board meeting recaps anytime—at home, on the road, or on your tractor.
Proud Partners of





Proposed SGMA fee (Tier 1 for all parcels; Tier 2 for ag acres and domestic users incl. private wells, up to $7.94/acre undistricted ag) goes to a May 18, 2026 public hearing. Winter recharge signed up 4,000+ acres and recharged ~3,600 AF in January. Staff noted WY2025 annual report figures show most indicators green.
Board ratified a cost-share agreement adding KNDLA into subbasin coordination costs, with projected annual amounts of about $23K or $37K depending on GSA size and possible additional cash calls. PMP demand-management policy work is underway; the ad hoc plans to meet after the holiday (early April). Outreach workshops may occur this summer after the annual plan is completed.
Basin conditions remain strong with groundwater levels recovered to pre-drought elevations and sustainability criteria met for WY2025. Extraction fees are increasingly burdening agricultural users, who now pay about three-quarters of costs based on pumping levels, and staff may bring a Prop 218/extraction-fee policy discussion at a future meeting (potentially April). Staff also canceled planned water budget modeling, reducing future consulting costs.
Water demand continues to decline and is largely price-inelastic (10% rate increase reduces demand ~2%). The study estimated ~37,000 households may face unaffordable bills. No formal action was taken; staff will gather more information on assistance programs (retailers and Sacred Heart) and may return to the committee.
State staff recommended denying Tule Subbasin exclusion requests; PID plans public comments ahead of the April 7 State Board meeting and related staff discussions. Growers must register wells and use GEARS before May 1, 2026. The Board approved a resolution continuing the ETGSA 2024 Amended GSP and 2024 Coordination Agreement as PID’s interim program.