September 2025 Other Meeting

Listen to AI Recap
Loading...

Top 3 Key Takeaways

Pure Water Southern California Program Cost Update: Staff presented updated cost estimates for the massive water recycling program, with Phase 1 now estimated at $8.3 billion for Metropolitan's portion (total $9.4 billion including Sanitation District costs). The program would produce 150 million gallons per day of recycled water through indirect potable reuse (90 MGD) and direct potable reuse (25 MGD), with water delivered through a 39-mile backbone pipeline to groundwater basins and industrial users.