November 2026 Board Meeting

Loading...

Top 3 Key Takeaways

1. DMC Subsidence Correction Project: Task 1 on Schedule and on Budget Concrete liner installation has begun in Pool 1, where crews reported placing roughly 600 feet per day. Shoulder drain installation is approximately 75% complete across the three pools, and liner geotextile installation is 90% complete in Pool 1. Staff reported no new safety issues. Based on the latest approved invoice, staff placed progress at 35.7% of the overall budget; that figure is not a measure of physical construction completion.