Solar Project Construction Management Contract Approved: The board unanimously approved a $378,470 contract amendment with Z&K Consultants for construction inspection services on the district's solar projects. The inspector will oversee the Horton Solar facility, Nancy Wright regional facility, and RES-BCT solar projects to ensure construction meets specifications and protects the district's long-term investment, with the project expected to generate $24 million in savings over 25 years.