1. CVC Pool Liner Repair and Nord Siphon Turnout Replacement Are on an Accelerated Timeline The Nord Siphon turnout replacement project on the Cross Valley Canal encountered a liner failure that required emergency repairs. A notice to accelerate construction was issued, with crews working nights and weekends. As of the meeting, the canal liner pour was completed early that morning, and staff expressed hope that water could be back in the canal by the middle of the following week — roughly a month ahead of the original schedule. Separately, staff flagged new deformities in the Pool 3 liner that are being assessed for possible near-term repair, with urgency tied to keeping the system ready if a wet year materializes.