1. Chowchilla Bypass Basin Base Bid Awarded The board approved a $1,058,830 construction contract with Cal Valley Construction for basin earthwork, interconnection structures between cells, a distribution channel, a spill structure, and perimeter fencing. Three add-alternate connection items were excluded. The award was below staff’s $1.679 million estimate. Seven bids ranged from about $1.06 million to $1.89 million. Staff described roughly two weeks for contract documents after the notice of award, followed by up to 10 days to mobilize and a 130-day construction window.