1. J-2 Sewer Conversion Budget Increased The board authorized the general manager to approve or ratify an agreement with the Department of the Army for Groundwater Quality Protection Program Area J-2-1. It increased the capital budget for Job #11472, Area J-2, by $4,980,000, from $420,000 to $5,400,000. The work supports septic-to-sewer conversions. The precise J-2-1 construction area will be identified after engineering, and a construction contract will return to the board for approval. General Manager Macy also reported state funding for phase two of M-2. Requests for water-line work and road work around the Nancy Wright facility were denied. Another $900,000 currently designated for M-2 may become available for J-2 work if engineering is completed quickly enough; the board did not approve a transfer.