November 2026 Board Meeting

Loading...

Top 3 Key Takeaways

1. Repaired recharge system could operate this season Repairs at the Teichert pump site are complete, including embankment work. A temporary screen is in place while the permanent fish screen remains pending. December 1 is the earliest date allowed under the diversion permit, but operation depends on the Cosumnes River reaching approximately 280 cubic feet per second at Michigan Bar. If flows permit, the district could use the repaired setup for groundwater recharge.